Doctor Cog Return Link

Fiscal Year 2024-2027 Transportation Improvement Program Projects
Denver Regional Council of Governments

Projects in order by Project Number


September 2024 Modifications


2007-078
Region 1 Bridge On-System Pool

Amendment Reason: Transfer $3,882,000 in federal Bridge On-System funds to new I25 Resurfacing project. Total project cost decreases.

Bridge On-System (Federal) Changed from $46,870,000 to $42,988,000

Existing Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Bridge On-System) $17,400,000 $9,620,000 $9,950,000 $9,900,000
State (Bridge On-System) $0 $0 $0 $0
Local $0 $0 $0 $0
Total $17,400,000 $9,620,000 $9,950,000 $9,900,000


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$0 $46,870,000 $0 $46,870,000

Pool Project Listing

This pool includes the following current projects. All pool project funding depicts federal and/or state funding only.


Agency/Project NameDescriptionNotesCost
Essential Culvert Repairs $13,220,000
Essential Wall Repairs$5,300,000
Preventative Bridge MaintenanceProactive work, including scour work, fiber wrap$8,500,000
Joint Treatments$6,800,000
Deck TreatmentsResurfacing/overlays$7,000,000
Bridge Essential RepairsGenerally reactive; girder cleanouts$6,040,000

Revised Funding Table


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Bridge On-System) $17,400,000 $5,738,000 $9,950,000 $9,900,000
State (Bridge On-System) $0 $0 $0 $0
Local $0 $0 $0 $0
Total $17,400,000 $5,738,000 $9,950,000 $9,900,000


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$0 $42,988,000 $0 $42,988,000

Revised Pool Project Listing

This pool includes the following current projects. All pool project funding depicts federal and/or state funding only.


Agency/Project NameDescriptionNotesCost
Essential Culvert Repairs $13,220,000
Essential Wall Repairs$5,300,000
Preventative Bridge MaintenanceProactive work, including scour work, fiber wrap$8,500,000
Joint Treatments$6,800,000
Deck TreatmentsResurfacing/overlays$7,000,000
Bridge Essential RepairsGenerally reactive; girder cleanouts$6,040,000



2007-096
Region 1 Surface Treatment Pool

Amendment Reason: Update pool projects and transfer $21,500,000 to new I25 Resurfacing project. Total project cost decreases.

Surface Treatment (State) Changed from $154,292,000 to $132,792,000
Pool Added - US285
Pool Added - CO35
Pool Removed - US-85
Pool Removed - I76
Pool Removed - I76
Pool Removed - I70
Pool Removed - I25

Existing Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
State (Surface Treatment) $36,057,000 $33,364,000 $42,187,000 $42,684,000
Local $0 $0 $0 $0
Total $36,057,000 $33,364,000 $42,187,000 $42,684,000


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$16,782,000 $154,292,000 $0 $171,074,000

Pool Project Listing

This pool includes the following current projects. All pool project funding depicts federal and/or state funding only.


Agency/Project NameDescriptionNotesCost
CO88 (Federal Blvd)Alameda Ave to Louisiana Ave$8,500,000
US-85H. Ranch Pkwy to C-470$3,000,000
CO86Woodlands Blvd to IREA Access$2,500,000
CO7I25 to US85$13,200,000
I76York St to Dahlia St$19,800,000
US85I76 to 124th Ave$8,100,000
SH-224I-25 to US-6$5,000,000
US40MP 252 to I70$12,000,000
SH-391Hampden Ave to Jewell Ave$4,000,000
US287I70 to 92nd Ave$10,100,000
SH-265I-70 to US-6$4,600,000
CO8Soda Lakes Rd to McIntyre St$1,000,000
DesignVarious Locations$2,000,000
I76Emergency Repair$782,000
I70MP 215.7 to MP 231$9,800,000
US85Florida to I25$3,000,000
CO74Evergreen DT to Cold Springs Gulch$7,200,000
US285Federal to Dahlia$10,800,000
CO83MP 70.9 to Mississippi$6,300,000
US619th to Colfax$6,500,000
I25MP 208 to 44th$12,300,000
AlamedaBryant to S Lipan St$3,500,000
CO88W Asbury to W Belleview$9,000,000
CO72I70 to W 52nd$5,000,000
CO1214th to 37th$5,100,000
MaintenanceVarious Locations$2,000,000

Revised Funding Table


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
State (Surface Treatment) $36,057,000 $11,864,000 $42,187,000 $42,684,000
Local $0 $0 $0 $0
Total $36,057,000 $11,864,000 $42,187,000 $42,684,000


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$16,782,000 $132,792,000 $0 $149,574,000

Revised Pool Project Listing

This pool includes the following current projects. All pool project funding depicts federal and/or state funding only.


Agency/Project NameDescriptionNotesCost
CO88 (Federal Blvd)Alameda Ave to Louisiana Ave$8,500,000
CO86Woodlands Blvd to IREA Access$2,500,000
CO7I25 to US85$13,200,000
US85I76 to 124th Ave$8,100,000
SH-224I-25 to US-6$5,000,000
US40MP 252 to I70$12,000,000
SH-391Hampden Ave to Jewell Ave$4,000,000
US287I70 to 92nd Ave$10,100,000
SH-265I-70 to US-6$4,600,000
CO8Soda Lakes Rd to McIntyre St$1,000,000
DesignVarious Locations$2,000,000
US85Florida to I25$3,000,000
CO74Evergreen DT to Cold Springs Gulch$7,200,000
US285Federal to Dahlia$10,800,000
CO83MP 70.9 to Mississippi$6,300,000
US619th to Colfax$6,500,000
AlamedaBryant to S Lipan St$3,500,000
CO88W Asbury to W Belleview$9,000,000
CO72I70 to W 52nd$5,000,000
CO1214th to 37th$5,100,000
MaintenanceVarious Locations$2,000,000
US285Pine Junction to Foxton Road$8,100,000
CO35I70 to I270$400,000



2016-002
Air Quality Improvements Set-Aside

Amendment Reason: Roll $2,000,000 in unspent funds from prior years into current set-aside program. Total project cost increases.

Congestion Mitigation / Air Quality (Federal) Changed from $7,200,000 to $9,200,000
Congestion Mitigation / Air Quality (Local) Changed from $1,799,000 to $2,299,000

Existing Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Congestion Mitigation / Air Quality) $2,420,000 $1,776,000 $1,626,000 $1,378,000
Local $605,000 $444,000 $406,000 $344,000
Total $3,025,000 $2,220,000 $2,032,000 $1,722,000
Project Phase to Initiate Other Phase Other Phase Other Phase Other Phase


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$0 $8,999,000 $0 $8,999,000

Revised Funding Table


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Congestion Mitigation / Air Quality) $4,420,000 $1,776,000 $1,626,000 $1,378,000
Local $1,105,000 $444,000 $406,000 $344,000
Total $5,525,000 $2,220,000 $2,032,000 $1,722,000
Project Phase to Initiate Other Phase Other Phase Other Phase Other Phase


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$0 $11,499,000 $0 $11,499,000



2022-031
East Colfax BRT: Civic Center Station to Yosemite

Amendment Reason: Add $23,111,000 in federal Capital Investment Grant funds. Total project cost increases.

Capital Investment Grant (Federal) Changed from $126,889,000 to $150,000,000
Capital Investment Grant (Local) Changed from $81,267,000 to $83,479,000

Existing Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Capital Investment Grant) $126,889,000 $0 $0 $0
Federal (Carbon Reduction Program) $2,845,000 $0 $0 $0
Federal (Congestion Mitigation / Air Quality) $5,686,000 $0 $0 $0
Federal (Surface Transportation Block Grant) $8,513,000 $0 $2,685,000 $0
Local $91,107,000 $0 $2,305,000 $0
Total $235,040,000 $0 $4,990,000 $0
Project Phase to Initiate CM/GC Construction None CM/GC Construction None


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$15,126,000 $240,030,000 $0 $255,156,000

Revised Funding Table


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Capital Investment Grant) $150,000,000 $0 $0 $0
Federal (Carbon Reduction Program) $2,845,000 $0 $0 $0
Federal (Congestion Mitigation / Air Quality) $5,686,000 $0 $0 $0
Federal (Surface Transportation Block Grant) $8,513,000 $0 $2,685,000 $0
Local $93,319,000 $0 $2,305,000 $0
Total $260,363,000 $0 $4,990,000 $0
Project Phase to Initiate CM/GC Construction None CM/GC Construction None


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$15,126,000 $265,353,000 $0 $280,479,000



Request
Reunited Denver Project: Globeville Elyria-Swansea

Amendment Reason: Add new project for federal discretionary award through the Reconnecting Communities and Neighborhoods Program.

New Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Neighborhood Access and Equity) $35,475,000 $0 $0 $0
Local $32,436,000 $0 $0 $0
Total $67,911,000 $0 $0 $0


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$0 $67,911,000 $0 $67,911,000



Request
I25 Resurfacing: Mile Post 208 to 214

Amendment Reason: Add new project with funding from the Region 1 Surface Treatment Pool and Region 1 Bridge On-System Pool.

New Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Bridge On-System) $0 $3,882,000 $0 $0
Federal (Strategic Safety Funds) $0 $1,000,000 $0 $0
State (Bridge On-System) $0 $0 $0 $0
State (Surface Treatment) $0 $21,500,000 $0 $0
Local $0 $0 $0 $0
Total $0 $26,382,000 $0 $0


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$0 $26,382,000 $0 $26,382,000