Fiscal Year 2024-2027 Transportation Improvement Program Projects
Denver Regional Council of Governments

Projects in order by Project Number


October 2024 Modifications


2008-103
Region 1 FASTER Bridge and Tunnel Enterprise Pool

Amendment Reason: Add $500,000 in state FASTER Bridge Enterprise funds and add one pool project. Total project cost increases.

FASTER Br. Enterprise (State) Changed from $49,450,000 to $49,950,000
Pool Added - Several Bridges in Region 1

Existing Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
State (FASTER Br. Enterprise) $7,700,000 $2,000,000 $15,000,000 $24,750,000
State (Legislative) $0 $0 $0 $16,250,000
Local $0 $0 $0 $0
Total $7,700,000 $2,000,000 $15,000,000 $41,000,000


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$29,844,000 $65,700,000 $0 $95,544,000

Pool Project Listing

This pool includes the following current projects. All pool project funding depicts federal and/or state funding only.


Agency/Project NameDescriptionNotesCost
I-70 WB Over US 6Clear Creek (Floyd Hill)$5,700,000
Speer and 23rd Bridge Replacements$60,000,000
I-76 over York St.E-17-GW and E-14-GV$12,535,000
I-70 over W. 32nd Ave.Replace 2 Bridges$13,773,000

Revised Funding Table


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
State (FASTER Br. Enterprise) $7,700,000 $2,500,000 $15,000,000 $24,750,000
State (Legislative) $0 $0 $0 $16,250,000
Local $0 $0 $0 $0
Total $7,700,000 $2,500,000 $15,000,000 $41,000,000


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$29,844,000 $66,200,000 $0 $96,044,000

Revised Pool Project Listing

This pool includes the following current projects. All pool project funding depicts federal and/or state funding only.


Agency/Project NameDescriptionNotesCost
I-70 WB Over US 6Clear Creek (Floyd Hill)$5,700,000
Speer and 23rd Bridge Replacements$60,000,000
I-76 over York St.E-17-GW and E-14-GV$12,535,000
I-70 over W. 32nd Ave.Replace 2 Bridges$13,773,000
Several Bridges in Region 1Bridge Prescoping$500,000



2020-059
US285/Broadway Operational Improvements

Amendment Reason: Project cancelled by sponsor and $6,369,000 in unused federal Surface Transportation Block Grant funds returned to DRCOG for reprogramming. $880,000 in unused local match removed as well. Total project cost decreases.

Existing Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Surface Transportation Block Grant) $0 $0 $0 $0
State (Regional Priority Projects) $0 $0 $0 $0
Local $0 $0 $0 $0
Total $0 $0 $0 $0


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$14,900,000 $0 $0 $14,900,000

Revised Funding Table


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Surface Transportation Block Grant) $0 $0 $0 $0
State (Regional Priority Projects) $0 $0 $0 $0
Local $0 $0 $0 $0
Total $0 $0 $0 $0


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$7,651,000 $0 $0 $7,651,000



2022-016
Region 1 Revitalizing Main Streets Pool

Amendment Reason: Add $250,000 in state Legislative funding and add one pool project. Total project cost increases.

Legislative (State) Changed from $250,000 to $500,000
Pool Added - Parker

Existing Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
State (Legislative) $250,000 $0 $0 $0
Local $0 $0 $0 $0
Total $250,000 $0 $0 $0


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$4,601,000 $250,000 $0 $4,851,000

Pool Project Listing

This pool includes the following current projects. All pool project funding depicts federal and/or state funding only.


Agency/Project NameDescriptionNotesCost
AuroraNorthwest Aurora Intersection Pedestrian Safety Enhancement$1,600,000
Edgewater25th Avenue Streetscape Project$841,000
Commerce City68th Ave. Multimodal Safety Improvements$1,420,000
EnglewoodSouth Broadway HAWK Signal$316,000
Lakewood40 West ArtLine Bike Path Lighting and Safety$424,000
Wheat RidgeMain Street Plaza, Event, and Park Space$250,000

Revised Funding Table


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
State (Legislative) $250,000 $250,000 $0 $0
Local $0 $0 $0 $0
Total $250,000 $250,000 $0 $0


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$4,601,000 $500,000 $0 $5,101,000

Revised Pool Project Listing

This pool includes the following current projects. All pool project funding depicts federal and/or state funding only.


Agency/Project NameDescriptionNotesCost
AuroraNorthwest Aurora Intersection Pedestrian Safety Enhancement$1,600,000
Edgewater25th Avenue Streetscape Project$841,000
Commerce City68th Ave. Multimodal Safety Improvements$1,420,000
EnglewoodSouth Broadway HAWK Signal$316,000
Lakewood40 West ArtLine Bike Path Lighting and Safety$424,000
Wheat RidgeMain Street Plaza, Event, and Park Space$250,000
ParkerPilgrim's Place Walkway$250,000



2022-018
CO7/95th Intersection Improvements

Amendment Reason: Remove $300,000 in state Legislative-Transit funding transferred to Project 2022-061. Total project cost decreases.

Legislative-Transit (State) Changed from $12,508,000 to $12,208,000

Existing Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Surface Transportation Block Grant) $0 $2,272,000 $0 $0
State (House Bill 1466 - MMOF) $0 $0 $0 $0
State (Legislative-Transit) $11,940,000 $568,000 $0 $0
State (MMOF) $2,800,000 $0 $0 $0
Local $4,436,000 $0 $0 $0
Total $19,176,000 $2,840,000 $0 $0
Project Phase to Initiate None Construction None None


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$4,860,000 $22,016,000 $0 $26,876,000

Revised Funding Table


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Surface Transportation Block Grant) $0 $2,272,000 $0 $0
State (House Bill 1466 - MMOF) $0 $0 $0 $0
State (Legislative-Transit) $11,640,000 $568,000 $0 $0
State (MMOF) $2,800,000 $0 $0 $0
Local $4,436,000 $0 $0 $0
Total $18,876,000 $2,840,000 $0 $0
Project Phase to Initiate None Construction None None


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$4,860,000 $21,716,000 $0 $26,576,000



2022-061
30th Street Complete Streets: CO119 to CO7

Amendment Reason: Add $300,000 in state Legislative funding transferred from Project 2022-018. Total project cost increases.

Added State Funding Legislative $300,000

Existing Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (MMOF - ARPA - DRCOG) $180,000 $0 $0 $0
Federal (Transportation Alternatives-DRCOG) $220,000 $0 $0 $0
State (House Bill 1466 - MMOF) $200,000 $0 $0 $0
Local $160,000 $0 $0 $0
Total $760,000 $0 $0 $0
Project Phase to Initiate Design None None None


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$240,000 $760,000 $0 $1,000,000

Revised Funding Table


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (MMOF - ARPA - DRCOG) $180,000 $0 $0 $0
Federal (Transportation Alternatives-DRCOG) $220,000 $0 $0 $0
State (House Bill 1466 - MMOF) $200,000 $0 $0 $0
State (Legislative) $300,000 $0 $0 $0
Local $160,000 $0 $0 $0
Total $1,060,000 $0 $0 $0
Project Phase to Initiate Design None None None


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$240,000 $1,060,000 $0 $1,300,000



Request
Vazquez and BNSF Early Warning Detection System

Amendment Reason: Add new project from CDOT Freight Investment Plan.

New Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Freight) $0 $510,000 $0 $0
Local $0 $0 $0 $0
Total $0 $510,000 $0 $0


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$0 $510,000 $0 $510,000



Request
US85 Steep Slope Repair

Amendment Reason: Add new project from CDOT"s Freight Investment Plan.

New Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Freight) $0 $4,200,000 $0 $0
Local $0 $0 $0 $0
Total $0 $4,200,000 $0 $0


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$0 $4,200,000 $0 $4,200,000



Request
Coordinated Adaptive Ramp Metering Expansion

Amendment Reason: Add new project for federal Strengthening Mobility and Revolutionizing Transportation discretionary award.

New Project


Four Year Funding by Funding Types
Funding TypeFederal Fiscal Year 2024Federal Fiscal Year 2025Federal Fiscal Year 2026Federal Fiscal Year 2027
Federal (Strengthening Mobility and Revolutionizing Transportation) $0 $1,473,000 $0 $0
Local $0 $0 $0 $0
Total $0 $1,473,000 $0 $0


Overall Funding
Prior FundingFour Year PeriodFuture FundingTotal Funding
$0 $1,473,000 $0 $1,473,000